June Regeneration Project Update

The regeneration team have shared another positive update on the project, with significant progress continuing to be made on Site 1 and exciting developments about to begin on Site 2.
Works at Site 1 continue to advance smoothly and remain fully on schedule. Both the roof and window installation phases are now very much underway and progressing well, marking another positive milestone for the works.
One of the most impressive aspects of the project so far that continues to surprise a lot of residents has been the considerate and discreet approach taken throughout construction. Many residents and visitors have commented that they were unaware works had even been taking place, despite the substantial progress that continues to be achieved behind the scenes. This is a real testament to the professionalism and careful planning of the team at Wolsey House Group, who have worked hard to ensure disruption has been kept to an absolute minimum while maintaining excellent progress towards the project.
Site 2 Set to Begin
Progress now also turns to Site 2, where work will officially commence on Monday 8th June with the start of demolition activities. This marks the first step in preparing the site for the next phase of development and represents another exciting milestone for the wider regeneration project.
As has been the case with Site 1, Wolsey House Group will continue to carry out works with a strong focus on minimising disruption to the surrounding community. Their proven track record at Site 1 gives us great confidence that works at Site 2 will be managed with the same care, professionalism and attention to detail.
Looking Ahead
It’s encouraging to see both sites moving forward, with Site 1 making excellent visible progress and Site 2 preparing to begin its transformation. We look forward to sharing further updates as work continues.